Automation · Regulated Manufacturing · Case Study

Modernizing Legacy Automation Systems

Lessons from a Regulated Manufacturing Project

Modernizing a legacy automation system involves more than replacing a PLC. It requires a structured approach to assessment, integration, testing, commissioning, and validation.

01

The Challenge

A regulated manufacturing facility needed to modernize its legacy automation platform while minimizing disruption to operations.

  • Modernize a legacy PLC platform
  • Relocate PLC, HMI, and Remote I/O panels
  • Integrate new equipment and instrumentation
  • Update SCADA applications
  • Support commissioning and validation activities
02

Why These Projects Are More Complex Than They Appear

Legacy modernization often requires much more than hardware replacement. Successful delivery depends on several connected engineering workstreams.

1

Existing System Assessment

Review the current control architecture, dependencies, and project constraints.

2

Migration Planning

Define how controls, panels, applications, and field devices will transition.

3

Network Updates

Plan communications and system-integration requirements across the platform.

4

HMI & SCADA Modernization

Update applications and operator interfaces for the new control architecture.

5

FAT & Simulation

Test the solution in a controlled environment before on-site deployment.

6

Commissioning & Validation

Support startup, qualification, and regulated project requirements.

03

Technical Approach

The execution combined controls migration, application modernization, simulation, field work, and regulated startup support.

  • PLC and HMI migration
  • New VFD control panel design and installation
  • EtherNet/IP and Modbus TCP integration
  • AVEVA InTouch 2023 modernization
  • Simulation environment development
  • Factory Acceptance Testing execution
  • Instrumentation installation
  • Commissioning and validation support
04

Project Execution

The project followed a structured path from initial assessment through commissioning and validation.

  1. STEP 01

    Assessment

  2. STEP 02

    System Design

  3. STEP 03

    Panel Design

  4. STEP 04

    PLC Migration

  5. STEP 05

    FAT Testing

  6. STEP 06

    Commissioning

  7. STEP 07

    Validation

05

Key Takeaway

Automation modernization is most effective when it is treated as a complete engineering initiative—not simply as an equipment replacement project.